Category Archives: Announcement

LELWD on ’60 Minutes’

LELWD Case Study Resulted in ’60 Minutes’ Story

Read the Case Study

As seen on “60 Minutes,” the Littleton Electric Light and Water Departments has publicized the case of foreign hackers targeting its computer systems. LELWD first made the announcement in March with the release of a case study to educate the utility industry and others on cybersecurity threats.

For more information, read LELWD’s public statement from March below and click here to read the case study. 

The LELWD issued the following statement on March 14, 2025:

LELWD Publicizes Case Study on Foreign Hackers Targeting U.S. Utilities

LITTLETON, MA – The Littleton Electric Light and Water Departments has participated in a case study with its cybersecurity provider that details the immediate steps taken to protect its computer networks after a 2023 intrusion by foreign hackers. There was no serious threat to public safety or customer data, and LELWD hopes publicizing the problem and solution helps utilities of all sizes act on the threats posed by foreign adversaries.

Here are key points to consider:

  • No customer-sensitive data was compromised.
  • In November 2023, the FBI alerted the LELWD that a Chinese cyberespionage group, Volt Typhoon, had access to its system. At that time, investigators told the LELWD that about 200 New England organizations were similarly affected.
  • The LELWD took immediate action and cooperated with the U.S. Cybersecurity and Infrastructure Security Agency (CISA) to install sensors to monitor the activity of the hackers. While in the system, it appeared the hackers accessed a file server that stores public records.
  • By December 2023, the federal government and the hackers were off the system. Last August, CISA returned to the LELWD to perform a two-week penetration test that showed the cybersecurity defenses working properly. The LELWD is a distribution company, and its systems do not have access to or control of the larger, critical electrical grid infrastructure. It appears the LELWD was targeted simply because its system used a firewall with a known security flaw. The then-managed service provider had not updated the firmware and as a result, was terminated.
  • The LELWD was already bolstering its cybersecurity to better monitor operational technology (OT) assets, security information technology and OT network traffic, and monitor communications between OT devices and systems. OT systems are used to control and manage physical equipment and processes.
  • The LELWD now contracts with managed served provider EvoLab Technology Solutions and uses a system monitoring platform from Dragos, Inc., a provider of OT cybersecurity technology for industrial and critical infrastructure. In addition, the LELWD’s network architecture was changed to render unusable any system information potentially obtained by the hackers.

“We were able to quickly isolate the threat in late 2023 before anything happened, and we accelerated our ongoing work to strengthen our cybersecurity. We worked with the U.S. Department of Homeland Security’s CISA, the FBI, the American Public Power Association, and our cybersecurity partners, EvoLab and Dragos, to protect our systems. We can now publicize this threat and solution to educate other small utilities. You would never think that you’d be targeted, but there is a real threat from foreign adversaries,” said Nick Lawler, General Manager of the LELWD.

The cybersecurity improvements were led by David Ketchen, Assistant General Manager, whose efforts were recognized by the state’s Executive Office of Technology Services & Security. Ketchen received the Cybersecurity & Risk Management award at the Massachusetts Excellence in Technology Awards in September 2024.

The LELWD was supported by the American Public Power Association, a national organization representing municipal electric utilities nationwide. Though its cybersecurity programs, the APPA has awarded more than $14 million to 32 utilities, funding 78 cybersecurity projects.

“The response to the LELWD breach was swift, according to Dragos. Investigators identified the attacker’s movements, including server message block traversal and remote desktop protocol lateral movement,” reported Infosecurity Magazine. “The compromised organization was able to contain the threat and reconfigure its network to prevent further exploitation. No customer-sensitive data was reportedly compromised.” ###

Customer Scam Alert! Click here for details

Please be aware of telephone scams.  LELWD will never seek immediate payment over the phone using a prepaid debit card or money order. LELWD does not contract with Eversource or another utility on service shut offs. If called about an instant payment or service disconnection, immediately hang up and call LELWD to verify your account status at 978-540-2222, Mon.-Thurs., 6:30 a.m. – 4:30 p.m.

Outdoor Watering Restrictions In Effect

Outdoor Watering Restrictions in Effect

Per MassDEP

Please Conserve Water

Due to dry weather affecting nearby river flows, MassDEP is requiring LELWD water customers to conserve and observe water restrictions as per the town’s Water Management Act permit.

The Water Use Restrictions, a condition of LELWD’s Water Management Act Permit from MassDEP, are:

  • All nonessential outdoor water uses are prohibited.
  • Nonessential outdoor water uses include:
    • irrigation of lawns via sprinklers or automatic irrigation systems;
    • washing of vehicles, except in a commercial car wash or as necessary for operator safety; and
    • washing of exterior building surfaces, parking lots, driveways or sidewalks, except as necessary to apply surface treatments such as paint, preservatives, stucco, pavement or cement.

The following uses may be allowed when mandatory restrictions are in place:

  • irrigation to establish a new lawn and new plantings during the months of May and September;
  • irrigation of public parks and recreational fields by means of automatic sprinklers outside the hours of 9 am to 5 pm; and
  • irrigation of lawns, gardens, flowers and ornamental plants by means of a hand-held hose.

Water uses NOT subject to mandatory restrictions are those required:

  • for health or safety reasons;
  • by regulation;
  • for the production of food and fiber;
  • for the maintenance of livestock; or
  • to meet the core functions of a business (for example, irrigation by golf courses as necessary to maintain tees, greens, and limited fairway watering, or irrigation by plant nurseries as necessary to maintain stock).

Private Well Owners

While private well owners are not required to comply with the water restrictions, we ask that they do their part to conserve water, as it all comes from the same aquifer.

WHERE CAN I GET MORE INFORMATION?

Residents and consumers are encouraged to call LWD with any questions at 978-540-2222.

Drought Monitoring

Paving Schedule

Paving & Planting Scheduled to Complete Sewer & Water Main Projects

The following paving related to LELWD projects is planned for the remainder of 2025.

Whitcomb Avenue

Paving is planned for the week of September 15. Work will take place in three phases with separate detours for each:

    1. Taylor St. to Sanderson Rd.
    2. Sanderson Rd. to Porter Rd.
    3. Porter Rd. to Route 2 Bridge
  • Expect detours between 7 a.m. and 4 p.m.
  • This will be a full-width paving.
  • Follow detour signs and use caution in this area. 

Meetinghouse Road

King Street
Common to Westford line

King Street
small area near I-495 bridge

Great Road
near Acton Toyota of Littleton

Paving is expected in October and November. This section will be updated when more information is available from the contractor.

Paving schedules are subject to change without advanced notice.

Milling grinds off the top layer of existing asphalt to prepare the surface for paving. Milled roads may not be immediately paved. Please proceed with caution.

The contractors are required to repair and seed damaged turf at the end of the project – typically after the final road paving. The project specifications call for any planting to occur between April 15 and June 1 or between August 15 and October 30.

For More Information On The Projects

Boxborough Water Main

Enter your email below to receive updates only when new content is added to this page*

This project will bring public water to about 1,100 residents living along the western edge of Boxborough, where drinking water wells are contaminated with PFAS and road salt

Construction Update

Updated August 18th, 2025

Water Main Installation & Well Project Progressing

Water Mains

The water main from the Whitcomb Avenue Water Treatment Plant to Boxborough has been nearly completed.

    • Paving on Whitcomb Avenue is now scheduled for September. (It was originally set for mid-August.)
    • Water main installation on Mass Ave./Route 111 in Boxborough is to begin August 25.

Trumbull Well Development

This project also includes the development of a new well. The Trumbull Well on Taylor Street will be installed in late summer, early fall of 2025. Building of the pump house will start shortly after.

This project cost is estimated at about $19.1 million in total. The estimated $10 million to extend the water main to Boxborough will be paid for by the new customers who benefit from the project.

The Trumbull Well will supply about a quarter-million gallons of water per day, of which less than 25 percent will be needed to meet the demand of the Boxborough customers and 75 percent of the water will go toward Littleton’s needs. 

 

The cost of developing the well is being split, with 24.5 percent (or about $2 million) to be paid for by Boxborough ratepayers through a betterment charge. The balance of about $6.9 million is to be paid for by all ratepayers, through regular rates and debt service, as it benefits the entire system.

Because this well is being developed to address PFAS contamination, the project qualified for a no-interest state loan. This will save all ratepayers a lot of money.

Paving Whitcomb Avenue

Paving on Whitcomb Avenue, from Taylor Street to the town line, is now scheduled for September. (While previously scheduled for August 11, construction and paving schedules are subject to change.)

It will be a permanent mill and overlay. Please note, we are required to wait at least three months, and sometimes longer, before applying the final layer of pavement over a trench patch to allow for settling. This reduces the potential for voids forming under the pavement which can result in potholes. We also make sure the new pipes are sealed tight and working properly so we don’t have to dig up new pavement to fix a problem.

Forum

Thank you for joining us for a public forum held on January 15th, at 7pm. You can watch the replay here. 

Click to View The Full Planset

For more information, watch the replay of the Boxborough Water Extension forum from July 26.

Watch the first Boxborough Water Line Extension Project Information Session from January 2023.

Click to Read The Full Letter

Pagacik Scholarship Winners

Pagacik Scholarship Winners to Study Engineering, Environmental Sciences

Three graduates from Littleton High School who will pursue degrees in engineering and environmental science have been awarded the Denise M. Pagacik Memorial Scholarship.

Tvisha Nanda, Kaitlyn St. Gelais, and Cainan Pletcher each received a $2,000 prize toward college tuition. This is the first year three winners have been chosen due to the strength of the applicants.

The scholarships are given in the memory of Denise M. Pagacik, the late wife of LELWD Commissioner Ivan Pagacik. A Littleton resident for more than 25 years, she was a loving mother who is remembered for her selfless commitment to the community and helping others. Two scholarships were funded by the Pagacik family and the third by LELWD.

“Tvisha, Kaitlyn and Cainan all have a track record of academic achievement, but perhaps most importantly, they have demonstrated a commitment to their community through volunteering and public service,’’ said Nick Lawler, LELWD’s general manager.

The competitive scholarships are awarded to LHS students pursuing engineering or environmental sciences – careers vital to the future of electric and water utilities.

  • Cainan will be attending Lehigh University for engineering.
  • Tvisha will be attending UMass Amherst to study biomedical engineering.
  • Kaitlyn will be attending the University of New Hampshire for environmental science.

Scholarship Leads to Engineering Career

Four years after receiving the Denise M. Pagacik scholarship from the LELWD, Littleton resident Paige Hornbeck is launching her career with the engineering firm Weston & Sampson in Manchester, N.H.

Paige graduated from the University of New Hampshire in May with a civil engineering degree, and recently joined the company’s structural and transportation sector, working with software for site plans and structural calculations.

Paige loves interacting with people and hopes to work her way into the field, engaging with community members and learning more about environmental sustainability. The 2021 Littleton High School alum thanked LELWD and her community for the support that helped guide her career path.

“Having that support from multiple sectors and knowing that people cared about putting me through college with this specific degree was really assuring,’’ she said.

July 8th, 2025

Devens Electric System

Littleton Electric to Operate and Maintain Devens Electric System

The Littleton Electric Light and Water Departments has signed an eight-year contract to maintain and operate the electrical system at Devens, a 4,400-acre mixed-use community with about 850 electrical meters.

The LELWD won the competitive bid conducted by MassDevelopment, the state’s development finance agency and land bank. MassDevelopment will pay the LELWD about $1 million annually to operate and maintain the system, plus provide additional funding for capital improvements. MassDevelopment will continue to manage customer service and billing.

“The LELWD is pleased to bring our award-winning service and reliability to the Devens community. This will benefit the Devens residents and businesses who can rely on the LELWD to maintain the system and work to prevent outages. This is also a win for the LELWD as we create a new revenue source and new opportunities for the professional development of our line crews and engineers,” said Nick Lawler, P.E., General Manager of the LELWD.

The LELWD assumed operations and maintenance on July 1, 2025. The additional revenue and service territory will allow the LELWD to strengthen its team of line crews and not impact rates or service for its existing customers.

The Wellesley Municipal Light Plant elected not to bid for the contract. Wellesley had served Devens since the early 2000s after assuming the role from the LELWD.

The municipal electric provider for Littleton and Boxborough, the LELWD has a reputation for reliable service and fast restoration of its infrequent outages. The LELWD has been recognized for eight consecutive years for excellence in reliability by the American Public Power Association. In 2024, the LELWD customers were without power for a total of 30 minutes, compared to national average of 149 minutes, according to the APPA data.

MassDevelopment is redeveloping the former military base into a community with 100 businesses and organizations employing about 10,000 workers and with about 1,900 residents.

July 7th, 2025

Taylor Street’s New Water Main

Taylor Street is getting a new water main to replace a 113-year-old main that has become constricted, which is like drinking out of a smaller straw.

Construction Area

Taylor Street between Whitcomb Avenue and Porter Road.

Scope of Work

Digging up and removing the 6-inch, cast-iron water main and replacing it with 8-inch ductile iron pipe. Connecting customers to a temporary water main during construction and then to the finished water main. Repaving of the road at end of the project. 

Detours

Expect daytime detours between 7 a.m., and 4 p.m. Detour is planned onto Porter Road and Whitcomb Avenue. 

Service Interuptions

Customers on the route can expect brief service interruptions when service lines are swapped over to the temporary and new water mains.

Timeline

The project kicks-off June 27 with the installation of a temporary water main. Digging in the roadway and detours will begin in early July. The work to remove and install the water main could take up to 40 days, but may be done sooner. The road will be repaved as soon as possible after the completion of work, as allowed by the road opening permit.

Water Main Installed in 1912

The cast-iron water main installed in 1912 was state-of-the-art for the time. Original water mains were made of wood and assembled like barrels. 

What else happened in 1912?